This guide is intended to teach a Project
Manager how to maximize the use of 3f Software Planner. This
guide is neither a manual nor an
introduction to 3f Software Planner.
If you are looking for that, please go to
the
tutorial section. There you will find
a short getting started guide to each
module in 3f Software Planner 2006.
To download this guide as a PDF file,
click here.
Everything in this guide applies to the base module unless otherwise
noted.
1. Project Management Using 3f Software Planner
Everything in 3f Software Planner evolves around time: how
much time is planned for tasks, how many tasks are planned for a project,
the time spent on individual tasks, the time remaining for each task, etc.
In addition, you have several handy tools available to you that, when used
correctly, will lessen your workload and get you more organized.
1.1 Pre Project Phase
When a new project is set up in the system,
the first thing that needs to be done is to define the
tasks in the project and estimate the number
of hours needed to complete each task. A task can be added in the
task list by anyone with access to the system. Before time can be tracked
on a task, that task must be set to "Allow Time Tracking" which can
either be done in the task particulars (Figure 1.) or in the task list
inside the optional Gantt diagram and Planning module (Figure 2.) If a
task is not set to allow time tracking, nobody can track time against the
task nor make time post entries.
Figure 1.

Project Manager Tip: Disable "Allow Time Tracking" if you want to
prevent anyone from working on a particular task. Note that
unless you have the optional Approval Management module, anyone can change
the status of the "Allow Time Tracking" checkbox. The Approved, Pending
and Rejected radio buttons are only visible if you have the Approval
Management module.
Project Manager Tip: With the optional Approval Management module,
the tasks
entered by Project Members will be listed
in the Approval Management section of each
project, thus pending approval by the project manager.
Figure 2.

2. The Project Phase
2.1 Approve Timesheets (Requires
Approval Management Module)
If you have the the Approval Management
module, then you can set up projects so that
all timesheets submitted by resources can be approved before the time spent is
included in the time reports (Project
Overview and Time Report). If you do not
have the Approval Management module, then
the time is included in the time reports as soon as a resource
has submitted the timesheet. In Figure 3,
you can see where you set the Time Sheet
Approval.
Figure 3.

2.2 Approval Management (Requires:
Approval Management Module)
Everything pending for approval is found
in the Approval Management section (see
Figure 4.) The Approval Management section
can only be accessed by the Project Manager or a user with an
Enterprise Manager login. The section is
divided into 3 groups: Timesheets, Tasks
and Requests.
Note: If you do not have the
Approval Management module, then everyone
have access to the same. In smaller
companies where the structure is
simple, this may actually work better.
2.2.1 Timesheet (Requires:
Approval Management Module)
To approve a timesheet, click the date
across the resource for whom you want
to approve the timesheet. Before you
approve the timesheet, you have the option
to adjust billable and non billable hours
and you can even edit the report. Finally,
you have the option to reject the
timesheet altogether (see Figure 5). If
a timesheet is rejected, the resource will
be notified by a red triangle next to the
date of the timesheet (see Figure 6).
Figure 4.

Figure 5.

|

Figure 6. |
Project Manager Tip: You will only
see the timesheet for the projects where
you are assigned as Project Manager, unless you
have an Enterprise Manager account, in
which case you will see all the resources' timesheets
in all the projects.
Project Manager Tip: Time worked on
non project tasks is not approved; hence
it is not listed on the timesheet for
approval.
2.2.2 Tasks Approval (Requires:
Approval Management Module)
Tasks are approved in the same way as
timesheets. Simply click on the task name,
review the detail, then choose whether to
approve or reject the task. You also have
the option to set the task to "Allow Time
Tracking" by checking that checkbox (see
Figure 7).
Figure 7.

2.2.3 Tracking Requests (Requires:
Approval Management Module)
When a new task or general request is entered, such request is
automatically listed under the requester's "My Requests" section. The
system tracks when the request was reviewed, by whom and the status (see
Figure 8).
Figure 8.

3. Unsubmitted Timesheet
The 3f Software Planner keeps track of all timesheets that have not been
submitted by the resources (Figure 9). Here you can see at a glance
the resources whose timesheets are pending submission.
Figure 9.

4. Project Status
The 3f Software Planner has number of tools that you can use for
you to see
the status of a project. However, the data delivered by these tools are
only as good as the data going into them. Therefore, before you retrieve any report from 3f Software Planner, you should first do the
following:
4.1 Review Remaining Hours for the Project
As a project manager, you should always stay on top of two things (1) how
much time has been spent on the project and (2) how much time remains. If
you can do these, then you are in good shape (provided that you
react to the signals you get).
When submitting a timesheet in 3f Software Planner, one requirement is that the person submitting the timesheet
should enter how many
hours he/she has left on the task that he/she is working on. This is done by making
an entry during timesheet submission (see Figure 10).
Figure 10.

Ideally, the remaining hours for a task is the sum of the
remaining hours entered by all the resources working on that particular task.
However, in reality, such ideal is difficult to attain. Therefore,
one of the most important jobs for a Project Manager is to review, and if
necessary, adjust the remaining hours on the tasks in the project.
In the 3f Software Planner, this is done under Task Remaining Hours found
in the Project Management node (see Figure 11). When this page is loaded,
all the tasks in the project are listed by task number. (You have the
option to rearrange the list and view the tasks by Phase). There are two
columns of particular importance: the "Rem.
Hrs." and "Res. Rem. Hrs."
Figure 11.

In the column "Rem. Hrs." is where you set the remaining hours for the task by
the number of hours you find appropriate. On the other hand, in the column
"Res. Rem. Hrs." is where you can see the sum of the remaining hours
entered (and/or approved) for all the resources working on the
task. You now have two options: (1) Click "Set Task" which updates the
remaining hours to be equal to the sum of remaining hours for all the
resources or (2) you can click the number to the right of the Set Task
button. In the subsequent form you can see the remaining hours broken
down by resource.
It is then your job as a Project Manager to review and adjust the
remaining hours. If this is regularly done, then your system is always up-to-date!
Project Manager Tip: If you enter 0 in the "Rem. Hrs." column, the
task is considered 100% finished. If a task is finished, it will no longer
be listed in the Project Time Tracking page and, therefore, time cannot be
tracked on that task anymore.
4.2 Reports Showing the Remaining Hours
There are several project reports that show the remaining hours.
Take a look at each of these reports to see which one you can use in your
organization.
4.3 Project Overview
The Project Overview report (see Figure 12) may be considered as the most
important report because it gives you a list of all the tasks in the
project, listing the number of hours that has gone into a project versus
the planned and remaining hours. It basically gives you the health of
your project and tells you the areas to which you should pay particular attention.
Figure 12.

The columns
Planned, Actual, and Rem. Hrs. are self-explanatory, so we won't spend any
time on that.
The "% +/-" column tells you, as a percentage, how much ahead or
behind plan a certain task is.
The "Planned/Actual" column tells you if a task is ahead or behind the plan in
terms of hours.
The "Planned/Current" column tells you (in hours) how much a task is
ahead or behind considering the remaining hours that you have set .
The "% Finished" column tells you how completed a task is.
This report has a counterpart, the Project Overview by Phase, where the same
data are shown but the tasks are grouped by project phase.
Project Manager Tip: Before you use the Project Overview report,
make sure that:
(a) Everybody has submitted his/her timesheets (basically, prevent
delaying timesheets).
(b) You review and approve the
timesheets (if you have the Approval Management module).
(c) Review the
remaining hours for the entire project.
4.4 Project Home
The Project Home report (see Figure 13) is a summary or snapshot of the
current project. On the main page you will see the client details,
completion percentage, a summary of the number of hours worked on the
project, as well as a summary of the errors and changes.
Figure 13.

You also have the option to print Project
Home. The printout (see Figure 14) gives
you a summary of the project. The summary
contains key data from the project. The
report was designed to be used in
management meetings, or if you are working
by the hour for your client, you can send
this report as part of your reporting
requirements.
Figure 14.

Project Manager Tip: Before you use
the Project Home report, make sure that:
(a)
Everybody has submitted his/her timesheets
(basically, prevent delaying timesheets).
(b)
You review and approve the
timesheets (if you have the Approval
Management module).
(c) Review the
remaining hours for the entire project.
5. Project Reports
Aside form the previous reports, 3f
Software Planner contains other project
reports that you may find useful. Each
report is listed below with a
short description of what they do and what
they can be used for.
5.1 Time Report
The Time Report (Figure 15) gives you an
overview of the hours worked on the
project. This report shows you the hours
worked (billable and non billable) and can
be grouped by resource, task, department,
approved by, etc. If you need to report to
clients how many hours have gone into a
project, then this is the report to use.
You can export the data to Excel and then
manually remove the Work Hours column so
that the client does not see the
difference between billable and non
billable hours.
Figure 15.

Project Manager Tip: Before you use the Time Report, make sure that:
(a)
Everybody has submitted his/her timesheets
(basically, prevent delaying timesheets).
(b)
You review and approve the
timesheets (if you have the Approval
Management module).
(c) Review the
remaining hours for the entire project.
5.2 Planned and Actual Work Distribution
Work distribution refers to what type of work is being planned or worked
on a project expressed as a percentage of all the
hours planned or worked on that particular project. When new tasks are added, one
of the requirements is to choose an activity. The activity says something
about the work being done on the task. For instance, if you are planning a
pre project meeting with a client, you may want to assign the activity
"Planning" or "Meeting". During the planning phase, you can use this as a guide to see if you are
allotting enough time for the various activities in the project by
reviewing the Actual Work Distribution report in similar projects. Figure
16 shows planned work distribution of a project.
Figure 16.

6. Tips and Tricks
Like most software applications, 3f Software Planner also has
functionalities and features that are not easily recognizable at first glance. In this chapter, you will be introduced to
some of these features including examples of how you and your team can use
them.
6.1 Project Resources (Requires Gantt Diagram and Planning Module)
A project resource is usually an individual (or sometimes an equipment) that you can add to a project
but who cannot log in to the system. A project resource
can be scheduled in the Gantt diagram, for whom the work schedule can be
printed and for whom the number of hours worked on tasks along with the
remaining hours for the tasks worked on can be entered. A project resource cannot be assigned to an error and change
item, nor can a project resource use the comment system.
You can use project resources when, for instance, you have an external
consultant working on a project that you need to schedule and track. Another example is if you are renting a special piece of equipment to be
used on a project, the time of use of which needs to be tracked.
6.2 Enterprise Resources (Requires: Gantt diagram and Planning Module)
Enterprise resources are in essence the same as project resources with
one notably difference: they are set up once in the system for use in
various projects just like regular login resources. In other words, you can
set up as many Enterprise Resources as you want and then assign them to any
project. The assigned resource can then be scheduled in the Gantt
diagram.
6.3 Usage of Project and Enterprise Resources (Requires: Gantt diagram
and Planning Module)
While login resources will always give the greatest amount of flexibility,
you can in the beginning consider to use only Project and Enterprise resources
while you get yourself acquainted with the system.
6.4 Canceling of Tasks
From time to time you may want to cancel a task in a project. Canceling a
task basically removes the task from the task list and prevents users
from tracking time against it. When a task is cancelled, the time that
had been tracked on such task remains in the system but will be grouped under "Canceled
Tasks" in the Project Overview report.
When a task is cancelled, the following happens:
1. The task is removed from the task list and Gantt diagram (if you have the
Gantt diagram module).
2. It is removed from the Project Time Tracking page, hence time can no
longer be tracked for the task.
3. On the Project Overview report, it is placed at the
bottom in a special section for cancelled tasks. In this way, you can see all
the time spent on a project with or without the
cancelled tasks.
To cancel a task, go to the "Tasks Remaining Hours" in the Project
Management section; next click Cancel across the task you want to cancel
(see Figure 17).
See Figure 17.

To "reactivate" a cancelled task, check "Show Cancelled" on the same
page. All cancelled tasks are listed at the bottom of the page. Simply
click the "Activate" link across the task you want to reactivate.
Note that after activating a task, you may want to move it in the task
list to a different position, because the newly activated task is assigned the next
available task number (not its original task number), placing it at the
bottom.
6.5 Project Grouping
Grouping projects together gives you an overview of the number of hours
spent into multiple projects that are not related to each
other. You can set up an unlimited number of project groups in which you
can include an unlimited number of projects from any client. You can
even include the same project in multiple project groups. Project
grouping can be helpful if you are working on multiple projects for the
same client, or if you work for multiple clients on a major project. You
can probably think of more ways this report can be helpful for you. The grouping of projects takes place in the Project Grouping node found right
under the Project node (see Figure 18).
Figure 18.

Note: To group projects together, your login must be Enterprise
Manager (that is, if you have the Approval Management module).
6.6 Finishing a Project
When a project is finished, there are a few things you need to do:
1. Go to the "Time Remaining Hours" in the Project Management section;
then click the button "Set all rem. hrs. to 0". Doing so will set the
remaining to 0 on all the tasks, identifying them as finished.
2. Check the "Uncommitted Timesheets" which is also found in the Project
Management section. If there are resources who have yet to file one or
more timesheets for the project, request that they do so.
3. If you have the Approval Management module, check and make certain
that there are no pending timesheets; otherwise, approve them.
4. Go to Project Home in the Project Management section; print the
Project Home report and file it.
5. Click the Project Name to open the page where the project is defined.
From the Status combo box, choose "Finished"; then click Save.
When a project is set to "Finished", the following happens:
1. Nobody can access the project anymore because it is removed from the
tree view.
2. The tree view becomes less cluttered with projects.
If needed, you can reactivate the project at any time by going to the
page where the project is defined and change the status from
"Finished" to "Ongoing."