Gantt diagram and Planning Module
This guide will show you how you get
started with the Gantt diagram and
Planning module. If you need more in-dept
explanation click the help menu, or press
Ctrl + Shift + H on your keyboard to view
a help file.
It is assumed that you have setup a 14 day
trial account on our hosted server or 3f
Software Planner installed on your own
server. It is furthermore assumed that you are familiar with the
functionality of the Base Module.
If you have not yet set up the trial
account go to
http://www.3fsoftwareplanner.com/start/
to do so.
The Gantt diagram and Planning module has the
following additional functionalities (over
the base module):
-
You can specify a work calendar for each
individual resource.
-
You can plan the project graphically
using a Gantt diagram.
-
You can plan what individual resources
should do on a given day.
-
You can view daily, weekly and monthly
plans
-
You can create "Enterprise Resources"
Getting Started
Step 1. Work Calendar
Click the
Tree View > Administrative > Work
Calendar
On the loaded page, click an existing
calendar to edit or add a new calendar by
clicking the Add New icon.
Step 2. Assign work calendar to a login
resource
Click the
Tree View > Resources > Login Resources
> Name of the resource
On the subsequent page you can choose a
different work calendar or edit the one
assigned to the resource. Any change you
make will not affect any master calendar.
Step 3. Plan using the Gantt
diagram
Click the
Tree View > Projects > Name of Client >
Project Name
> Gantt Diagram
Start entering a new task by clicking "Add
Task Here". When you have entered the task
name click Enter on the keyboard. Navigate
to the next column using the arrow on your
key board. To activate a column for input
press the Enter key on the keyboard. We
strongly suggest that you review the help
files for the Gantt diagram.
Note: Any task entered in
the Gantt diagram is immediately available
in the Task List.
Step 4. Plan resources in the Gantt
diagram
|
Assuming you are still in the Gantt
diagram click the task you want to
plan a resource. Next click the link
"Click on a task, then click here to
open scheduling pane. |
A scheduling pane will now open below the
Gantt diagram listing all the resources
working on the project. All the days
covered by the task duration are listed
across from each login resource. Enter the
number of hours you want to plan a
resource for the on a given day.
Note: When you plan a resource on a
task, the hours you plan are shown on the
resource's Today
Step 5. View work schedule -
Enterprise Level
Click the
Tree view > Enterprise > Work Schedule
On the page that loads click the link
"Click to view" across from the resource
you want to see the work schedule.
Step 6. View work schedule -
Project Level
Click the
Tree view > Projects > Name of Client >
Project Name > Project Reports > Work
Schedule
On the page that loads click the link
"Click to view" across from the resource
you want to see the work schedule.
Step 7. Setup Enterprise Resources
Click the
Tree View > Resources > Enterprise
Resources
Information: An enterprise resource
is a resource that does not have a login
to the system. Enterprise resources can be
assigned to a project in the same fashion
as a regular login resource. If you do not
have the Approval Management module all
enterprise resources in the system are
automatically assigned to any new project.
Step 8. Setup Project Resources
Click the
Tree View > Resources > Enterprise
Resources
Information: An project resource is
a resource that does not have a login to
the system and which can only be used
within a the project where it was added.
If you do not have the Approval Management
module all enterprise resources in the
system are automatically assigned to any
new project.
Information about Enterprise and
Project resources: Enterprise
and Project resources are typically used
when you want to schedule objects like
cars, meeting rooms, equipment etc. They
can also be used if you have third party
consultants who work on projects from time
to time. The system allows you to setup an
unlimited number of enterprise or project
resources as well as plan these resources
in the Gantt diagram. You can enter actual
time used for each resource which, if you
do so, automatically is flows into the
time reports.
Inform your coworkers
Now that you have a general idea of the
new features added with the Gantt diagram
and Planning module inform you coworkers
about the following: