Remaining hours on a task

 

Applies to
Server version 3.4.0

 

Topic

This article explains how you set the remaining hours on a task during timesheet submission

 

Prerequisites  

None

 

See also

Set a task to finished

 

Article

When you submit a timesheet one of the requirements is that you enter the remaining hours you have left on a task.  This is done in the Rem. Hrs. field. on the submit timesheet page. The remaining hours are used by the project manager (if you have the Approval Management module) or the person is in charge of the project if you do not as basis for adjusting the remaining hours left on the project.  Adjusting the remaining hours in the project is done on the Task Remaining Hours Page in the project management section.

 

If you leave the Rem. Hrs. field blank, the system will display a message box with the following text:

 

You have not entered your remaining hours for one or more tasks in the Rem. Hrs. field. If you continue without entering the remaining hours, the system will assume that you have 0 remaining hours on the task(s) and enter that for you. Do you want to continue without entering the remaining hours?

 

If you choose to ignore this message box the system will then enter 0 hours on your behalf for the task or tasks you are submitting timesheet for. In the Project Management console you will be listed as having 0 hours left on the task.

 

It is important to understand, that the system does not calculate the remaining hours you have left on a task.  You must estimate how many hours you have left on the task.  While this does require a little extra work, and forces you to sit down and evaluate how much time you have left, the end result is more accurate.

 

 

 

 

Keyword

submit, timesheet, remaining, rem, hrs, rem. hrs., approving, timesheet submission, submission of timesheet, balance, balance hours, remaining hours, remaining hours on a task, remaining time on a task, task remaining, time remaining

 

 